| Facility Type | Community Park |
| Location | Hayward |
| Estimated Start Date | Spring 2024 |
| Estimated Completion Date | Summer 2026 |
| Total Project Budget | $5,000,000 |
| Project Manager | Diane Hardy 510-453-9970 hard@haywardrec.org |
Resolution 2425-04 Approved 2024 07 15Resolution 2425-04 Approved 2024 07 15
This project provides for the renovation of the existing Mt. Eden Park in Hayward. These include: Upgrades to sports field and court lighting, concrete and asphalt pavement repairs, fitness court, court resurfacing, and pathway enhancements.
New play equipment was installed in 2025 at the public playground.
Construction on the rest of the park improvements is underway and will be completed in the fall of 2026.