Details

Facility Type Trails, Linear Parks, & Greenways
Location Hayward
Estimated Start Date Summer 2017
Estimated Completion Date Fall 2019
Total Project Budget $1,208,390
Project Manager Hai-Ping Mo
(510) 888-5747
moha@haywardrec.org

Project Description

CPRS 2020 Award of Excellence

The Hayward Community Garden Phase 1 Improvement project has been awarded a California Parks and Recreation Society (CPRS) 2020 Award of Excellence in Design – Park Planning.

Project Description

This project provides for the development of a master plan and construction of Phase 1 improvements for the community garden site located at Whitman Street and Berry Avenue.

Community Meeting

A community meeting was held at the site on Wednesday, September 28, 2017 to review the garden concept plan.

Phase 1 Improvements

The Phase 1 Improvements include 70 garden plots with irrigation, raised beds, a small orchard, shade structure to accommodate outdoor classes, produce counter, seed library, demonstration garden, storage shed, compost, small greenhouse, pathways, and fencing and gates. A zone for community socializing will feature a picnic area with barbeques, “kiwi tunnel”, and a natural play area with art and a mural.  The Phase 1 Improvements were completed in fall 2019.

 

Project Status

Complete

Project Images