Facility Type | Local Park |
Location | District-Wide |
Estimated Start Date | Summer 2017 |
Estimated Completion Date | Fall 2022 |
Total Project Budget | $5,000,000 |
Project Manager | Darcie DeLashmutt (510) 750-4723 deld@haywardrec.org |
Fairmont Terrace Staff Report_9.10.18
Fairmont Terrace Staff Report_8.19.19
Fairmont Terrace Staff Report_6.15.20
Fairmont Terrace Demolition Staff Report_7.20.20
This project provides for the design and construction of park improvements and expansion of an existing 1.67-acre park to 5 acres. Improvements include on-site ADA parking, a new restroom building, two playgrounds, half basketball court, group picnic areas, small and large dog parks, open lawn, pathways, and a hillside trail.
Construction of the park is complete and the park is now open to the community.